Responsibility Allocation and Delay Mitigation Strategies in Owner-Initiated Changes in Ethiopia: A Case Study of the Nyala Insurance Headquarters Building Project
This case study of the Nyala Insurance Headquarters Building in Ethiopia reveals that owner-initiated changes, particularly MEP modifications, are the primary cause of construction delays, highlighting the critical need for early design finalization, clear accountability, and proactive monitoring to mitigate such impacts.
Original paper licensed under CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). This is an AI-generated explanation of the paper below. It is not written or endorsed by the author. For technical accuracy, refer to the original paper. Read full disclaimer
Building a skyscraper is rarely a straight line from blueprint to ribbon-cutting. It is a complex negotiation between the person who wants the building, the team that designs it, and the crew that builds it. When the person who owns the project decides to change their mind after construction has already started—perhaps wanting a different type of glass for the windows or a new layout for the electrical systems—this is known as an owner-initiated change. While these changes might improve the final building, they often act like a sudden detour on a long road trip, forcing the construction crew to stop, rethink, and sometimes undo work they have already finished. In developing economies, where materials might need to be shipped from abroad and money can be tight, these detours can be especially costly, leading to significant delays and financial strain. Understanding who is responsible when these changes happen and how to fix the resulting delays is crucial for keeping large projects on track.
Researchers recently looked closely at one such project to understand these dynamics: the Nyala Insurance Headquarters Building in Addis Ababa, Ethiopia. This massive commercial tower, rising eighteen stories above the city with three basement levels, was meant to be a straightforward construction job. However, the project hit a major stumbling block. After the original contract was terminated due to schedule slippage, the project resumed under an amended contract signed in August 2023 with the same contractor, China Wu Yi Co. Ltd. During this second phase, the building's owners made repeated changes to the design, specifically targeting the glass curtain wall that wraps the exterior, the mechanical and electrical systems inside, the interior finishes, and even some structural elements. The researchers, a team from Mekelle University and China Wu Yi Co. Ltd., wanted to know exactly how these changes affected the timeline, who was held accountable for the delays, and whether the strategies used to fix the problems actually worked.
To find the answers, the team did not rely on broad surveys or computer models. Instead, they dug into the actual history of this single building. They gathered project records, read through official letters and contracts, and interviewed the people who were there—the project managers, the engineers, and the site supervisors. They also walked the construction site to see the physical reality of the work, checking if the progress reports matched what was actually standing on the ground. By piecing together these different sources, they built a clear picture of what went wrong. They found that out of fifty distinct events that caused the project to fall behind schedule, the most frequent culprit was the owner changing their mind. These owner-initiated changes were responsible for 38 percent of all the delays. The next biggest problem was the time it took to get approval for those changes, which accounted for another 24 percent.
When the researchers broke down the types of changes, a clear pattern emerged regarding which ones caused the most trouble. The most disruptive changes involved the mechanical, electrical, and plumbing systems, often referred to as MEP. There were seven separate instances where these systems were altered, and on average, each change pushed the project back by sixty days. This is because these systems are deeply interconnected; changing a pipe or a wire often means tearing out walls or ceilings that have already been built. The second most problematic category was the curtain wall, the glass and metal skin of the building. Five changes were made here, causing an average delay of forty-five days per change. The researchers noted that the procurement for these glass panels was delayed by more than six months, a separate but related issue that compounded the problem. Changes to the interior finishes and the structural design also caused delays, but they were less frequent and shorter in duration than the mechanical and exterior work.
The study also looked at the human and financial side of the equation. The project had a total of 430 million Ethiopian birr in listed payments, but 95 million of that remained unpaid at the time of the study. This unpaid amount, representing about 22 percent of the total, created a significant bottleneck. While the contracts clearly stated who was supposed to do what, the reality on the ground was messier. The owners were slow to approve new designs, the consultants took too long to sign off on drawings, and the construction team struggled with staffing shortages and weak planning. The researchers found that while everyone had a job description, the coordination between them was often broken. Decisions were delayed, instructions were unclear, and the flow of information was inconsistent, which made it difficult to recover from the inevitable changes.
To combat these delays, the project team tried several strategies, including formal notices, contract amendments, and change orders. The most successful tool was the change order, a formal document that officially recorded a change in the work and its cost. This method was implemented 100 percent of the time and was rated as highly effective. However, the least effective strategy was monitoring and reporting. The team only managed to implement this half of the time, and it was rated as the least effective measure. The researchers found that without consistent, up-to-date reports on what was happening on the site, the owners and consultants could not see the problems coming or react quickly enough to fix them. The average effectiveness of all the mitigation strategies combined was moderate, suggesting that while the tools existed, they were not being used consistently or proactively enough to save the schedule.
The final conclusion from this deep dive into the Nyala Insurance project is that building a skyscraper in a complex environment requires more than just good intentions. The study shows that when owners make changes late in the game, the ripple effects can be severe, particularly for mechanical systems and exterior facades. The delays were not caused by a single failure but by a chain reaction of slow approvals, payment issues, and poor communication. The researchers suggest that the only way to prevent this is to finalize designs early, make decisions quickly, and ensure that everyone from the owner to the site engineer is on the same page. Without these proactive steps, even the most well-funded projects can find themselves stuck in a cycle of rework and waiting, turning a planned timeline into a much longer and more expensive reality.