A delivery gap in electricity grid expansion

This paper analyzes a novel dataset of over 900 European transmission investments to reveal that administrative delays and a tendency to treat projects as optional rather than committed have caused commissioning timelines to exceed official estimates by an average of 4.1 years while resulting in high cancellation rates, thereby inflating investment pipelines and undermining the reliability of grid expansion plans needed to meet 2040 climate targets.

Original authors: Damiano Alessi, Behnam Zakeri, Kavita Surana

Published 2026-10-07
📖 5 min read🧠 Deep dive

Original authors: Damiano Alessi, Behnam Zakeri, Kavita Surana

Original paper licensed under CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). ✨ This is an AI-generated explanation of the paper below. It is not written or endorsed by the authors. For technical accuracy, refer to the original paper. Read full disclaimer

The world is trying to change how it makes and uses energy. The goal is to move away from burning fossil fuels and toward clean power like wind and solar. This shift requires a massive upgrade to the electrical grid, the vast network of wires and towers that carries electricity from where it is made to where it is used. For this transition to work, new power lines must be built to connect remote wind farms and solar fields to cities and factories. However, building these lines is not just a matter of laying cable; it is a complex legal and administrative journey that crosses many different towns, regions, and countries. If the grid cannot be built fast enough, the clean energy it is meant to carry will have nowhere to go, leaving the climate goals out of reach.

A new study from researchers in Vienna has taken a close look at how long this process actually takes in Europe, the region with the most advanced and coordinated grid planning in the world. By examining over 900 specific investment projects planned over a 16-year period, the team discovered a significant gap between what officials say will happen and what actually gets built. They found that the average time to get a new transmission line ready for use is about 14.1 years, which is significantly longer than the official estimates of 10 years. More importantly, they found that the physical act of building the line takes less than three years. The vast majority of the time—more than 70 percent—is spent on paperwork, planning, and getting permission from various authorities.

The researchers did not just look at finished projects; they tracked the entire life cycle of these investments, from the moment they were first considered to the day they were either completed or abandoned. They found that the process is fraught with uncertainty. About 55 percent of the projects they tracked faced delays, averaging nearly five years past their original deadlines. Even more striking, nearly half of all the investments that were announced and put into the planning pipeline were eventually canceled or withdrawn before they could be built. This suggests that the list of projects currently on paper is much larger than the list of projects that will actually be delivered.

One of the key reasons for this high cancellation rate is how the people in charge of building the grid approach their work. The study suggests that grid operators often treat these planned projects as options rather than firm commitments. Because the future location of power plants and the demand for electricity are uncertain, operators secure the right to build a line but wait to see if the conditions are right before spending the money to actually do it. If the conditions change or the project becomes too difficult, they let the option expire and cancel the plan. While this protects the operators from financial risk, it creates a misleading picture for everyone else. The official plans show a pipeline of future capacity that looks robust, but in reality, a large portion of that capacity may never materialize.

The study also looked at why projects get stuck. While public opposition and environmental concerns are often cited as major hurdles, the data showed that the biggest delays happen early on, during the planning and permitting phases. Even when projects are cross-border, which usually implies a higher level of political coordination, they still face significant delays. The researchers noted that recent changes in European laws intended to speed up the process have helped, but they have not been enough to overcome the structural slowness of the system. The time spent waiting for approvals is so long that it creates a bottleneck, preventing the grid from expanding fast enough to meet the urgent needs of the energy transition.

The consequences of these delays are not just theoretical; they have real economic and environmental costs. The researchers calculated that if the current rate of failure and delay continues, the world could lose hundreds of billions of euros in economic welfare by 2040. It would also mean that a massive amount of clean energy, equivalent to the entire electricity consumption of the European Union in a single year, would be wasted because there is no grid to carry it. Furthermore, the inability to build the necessary infrastructure would force the continued use of fossil fuels, leading to a significant increase in greenhouse gas emissions.

This research highlights a critical flaw in how we plan for the future. The current system relies on optimistic timelines that do not account for the high probability of projects being delayed or canceled. The authors argue that we need to change how we view these investment plans. Instead of treating the list of announced projects as a guarantee of future capacity, we should treat it as a list of possibilities, many of which will not happen. To fix this, they suggest that regulators need better data and stricter rules. They propose that project promoters should be held accountable for their timelines and that the public should be given a clearer, more realistic picture of what can actually be built. Without these changes, the gap between our climate goals and our ability to build the necessary infrastructure will only widen, threatening the success of the global energy transition.